Practice Test Question-Disaster Recovery Planning

Practice Test Question-Disaster Recovery Planning

Practice Test Question-Disaster Recovery Planning

Preparing for your next security certification exam? After trying your hand at this practice test question, join the FREE CertMike Study Group for the CISSP, Security+, CySA+, PenTest+, CISM+ or SSCP certification to receive new questions each week. You’ll also receive free access to my customized study strategies.

Roger’s organization recently activated their disaster recovery plan in response to a facility emergency. At what point would the organization typically deactivate the plan?

A. When senior leaders arrive on scene to take command

B. When the organization has a stable operating environment set up in an alternate facility

C. When the organization is returned to its normal operating environment

D. When the organization completes the initial response effort

Correct Answer: C

Disaster recovery plans guide work during all stages of a disaster, from the initial response through the restoration of normal activity. The plan remains active until the organization is restored to its normal operating environment. This is our correct answer.

 

Get a copy of my official CertMike Practice Test books for the Security+ exam, CISSP exam, SSCP exam, or CySA+ exam and practice with hundreds of questions designed just like the real test!